8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 1Assignment lecture #3 1. Construct an AON network based on the following:ACTIVITY IMMEDIATE

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 1

Assignment lecture #3
1. Construct an AON network based on the following:

ACTIVITY IMMEDIATE PREDECESSOR(S)
A –
B –
C –
D A, B
E C

2. Insert a dummy activity and event to correct the following AOA network:

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 2

Assignment (cont’d)
3. The City Commission of Nashville has decided to build a botanical garden and picnic area in

the heart of the city for the recreation of its citizens. The precedence table for all the
activities required to construct this area successfully is given.

CODE ACTIVITY DESCRIPTION
TIME (IN
HOURS)

IMMEDIATE
PREDECESSOR(S)

A Planning Find location; determine resource requirements 20 None
B Purchasing Requisition of lumber and sand 60 Planning
C Excavation Dig and grade 100 Planning
D Sawing Saw lumber into appropriate sizes 30 Purchasing
E Placement Position lumber in correct locations 20 Sawing, excavation
F Assembly Nail lumber together 10 Placement
G Infill Put sand in and under the equipment 20 Assembly
H Out-fill Put dirt around the equipment 10 Assembly
I Decoration Put grass all over the garden, landscape, paint 30 Infill, out-fill

a) Draw the Gantt chart for the whole construction activity.
b) Draw the AON network for the construction activity.
c) Draw the AOA network for the construction activity.

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 3

Assignment (cont’d)
4. The planning department of an electronics firm has set up the activities for developing and production of a

new MP3 Player. Given the information below, develop a project network using Microsoft Project. Assume a
five-day workweek and the project starts on January 4, 2020.

Activity ID Description Activity Predecessor Activity Time (weeks)

1 Staff None 2
2 Develop market program 1 3
3 Select channels of distribution 1 8
4 Patent 1 12
5 Pilot production 1 4
6 Test market 5 4
7 Ad promotion 2 4
8 Set up for production 4, 6 16

The project team has requested that you create a network for the project, and determine if the project can
be completed in 45 weeks.

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

Individuals working in educational leadership positions may find themselves in situations where they must examine the legal and ethical guidelines for

Individuals working in educational leadership positions may find themselves in situations where they must examine the legal and ethical guidelines for determining whether an employee should be retained, disciplined, or terminated. In situations where there are reasonable arguments for these scenarios, it can be difficult to discern a correct decision. In

Description‫المملكة العربية السعودية‬ ‫وزارة التعليم‬ ‫الجامعة السعودية اإللكترونية‬ Kingdom of Saudi Arabia Ministry of Education Saudi

Description ‫المملكة العربية السعودية‬ ‫وزارة التعليم‬ ‫الجامعة السعودية اإللكترونية‬ Kingdom of Saudi Arabia Ministry of Education Saudi Electronic University College of Administrative and Financial Sciences Assignment 1 Communications Management (MGT 421) Due Date: 5th October 2024 @ 23:59 Course Name: Communication Management Student’s Name: Course Code: MGT421 Student’s ID Number:

Description‫المملكة العربية السعودية‬ ‫وزارة التعليم‬ ‫الجامعة السعودية اإللكترونية‬ Kingdom of Saudi Arabia Ministry of Education Saudi

Description ‫المملكة العربية السعودية‬ ‫وزارة التعليم‬ ‫الجامعة السعودية اإللكترونية‬ Kingdom of Saudi Arabia Ministry of Education Saudi Electronic University College of Administrative and Financial Sciences Assignment 1 Organization Design and Development (MGT 404) Due Date: 05/10/2024 @ 23:59 Course Name: Student’s Name: Course Code: MGT404 Student’s ID Number: Semester: First

Hide Assignment InformationInstructionsIn this project, you will develop a detailed comparative analysis of cloud vendors and their services. A comparative

Hide Assignment InformationInstructionsIn this project, you will develop a detailed comparative analysis of cloud vendors and their services. A comparative analysis provides an item-by-item comparison of two or more alternatives, processes, products, or systems. In this case, you will compare the pros/cons of the cloud service providers in terms of